Parallel Parkway

This new Woodruff Road bypass runs parallel to Woodruff Road and feature roundabouts with connections to Green Heron Drive, Ketron Court, Woodruff Industrial Lane and Verdae Boulevard.

The project scope includes construction of approximately 2,250 linear feet of new two-lane roadway between Verdae Boulevard and Woodruff Industrial Lane, with roundabouts constructed at the intersections of Ketron Court and Green Heron Road.

Additional improvements include the construction of a right-turn lane on Verdae Boulevard and a right-turn lane on Woodruff Industrial Lane, as well as improvements to Woodruff Industrial Lane from the intersection of the new road to the existing curb and gutter.

Update: JULY 2019

  • Intermediate paving completed between Verdae and Green Heron
  • Intermediate paving completed
  • Roundabouts at Ketron Court and Green Heron Drive are near completion
  • Storm drainage and concrete work on Woodruff Industrial currently underway
  • Light pole bases and conduit completed
  • Intermediate paving between Green Heron and Woodruff Industrial near completion